How Computing Power Can Be Accessed on Demand—Observations from Jiangsu's 1ms Urban Computing Network Construction
6 hour ago / Read about 0 minute
Author:小编   

Recently, the 1ms Urban Computing Network China Tour expert symposium and special investigation activities were held in Nanjing, Wuxi, and Suzhou, Jiangsu Province. This series of activities was launched in early 2025 and has already visited multiple provinces and cities. At the symposium, representatives of Jiangsu's basic telecommunications enterprises and computing network application enterprises exchanged views on practices related to millisecond-level networks, computing access, and inter-computing interconnection. Data shows that as of the end of July 2026, Jiangsu had more than 300 computing centers in use, with a computing scale in use exceeding 250 EFlops (FP16), and the province has basically formed a computing latency circle of "1ms within cities and 3ms within the province."