In a picture taken on April 2, 2019, a visitor tests a smartphone using the 5G network at a pop-up store of South Korean telecom operator LG Uplus in Seoul. - South Korea launches the worlds first fully-fledged 5G mobile networks on April 5, a transformational leap that already has superpowers sparring for control of an innovation expected to dominate the day-to-day lives of billions of people. Photo credit should read JUNG YEON-JE/AFP via Getty Images
LG Uplus's board approved up to 789 billion won (approximately $592 million) on Thursday to build phase 3 of its Paju AI data center in South Korea. Using Edaily's per-building power figures, that ceiling works out to the same cost per megawatt as phase 2. The three board approvals total over 2.75 trillion won, or about $2.07 billion and roughly 30% of the company's equity by TechTimes' calculation, and LG Uplus said customer demand is confirmed for all four buildings, though contracts for Buildings 2 through 4 remain undisclosed.
For investors and prospective tenants, the number to hold is the rate, not the total: about $10.8 million of approved ceiling per megawatt of campus power, a benchmark for what building, cooling and related equipment cost before any customer installs a GPU.
| Phase | Approved ceiling | Share of equity | Scope as reported | Board date |
|---|---|---|---|---|
| 1 | 615.6 billion won (about $462 million) | 7.02% | Building 1 | April 29, 2025 |
| 2 | 1.3489 trillion won (about $1.01 billion) | 14.88% | Buildings 2 and 3 | July 29, 2026 |
| 3 | 789 billion won (about $592 million) | 8.70% | Building 4, per WOW TV | Nov. 19, 2026 |
The phase 3 amount equals 8.70% of LG Uplus's equity of 9.0675 trillion won ($6.80 billion), with spending scheduled from Nov. 23, 2026 through January 2029. Phase 1 was disclosed April 29, 2025 and phase 2 on July 29, 2026, covering Buildings 2 and 3 with investment running through November 2028. WOW TV reported that phase 3 funds Building 4, a scope Digital Daily's account of the filing does not spell out.
The 2.75 trillion won ($2.07 billion) total is TechTimes' sum of ceilings, not a company figure and not money spent. Sateconomy described the phase 3 amount as approval limits, not actual spending, and Digital Daily noted it may change with business conditions during execution. Neither outlet named a funding source. Sateconomy also reported that phase 2's ceiling was 130% of the expected cost to absorb price and exchange-rate swings, which implies a base estimate near 1.04 trillion won ($778 million), and that the company set the phase 3 limit at a similar level. Chinese-language coverage cited the company on the same 130% convention for phase 3, which would put its base near 607 billion won ($455 million). If both hold, the ceilings sit about 30% above the underlying estimates, so the summed total reads as an upper bound rather than a forecast. The sum also excludes a 105.3 billion won ($79 million) purchase of land and building contracted in 2024.
Edaily reported that Paju's 200 MW campus splits into Building 1 at 51 MW, Building 2 at 21.5 MW, Building 3 at 72.5 MW and Building 4 at 55 MW. Dividing each phase's ceiling by the buildings it funds gives about 12.1 billion won ($9.1 million) per megawatt for phase 1, and about 14.35 billion won ($10.8 million) per megawatt for both phase 2 (Buildings 2 and 3, 94 MW) and phase 3 (Building 4, 55 MW). That is TechTimes' arithmetic, and it carries caveats: the per-building split comes from one translated report, LG Uplus has not published per-building capital costs, the ceilings include the reported buffer, and land is excluded.
The 200 MW figure is receiving power capacity, not IT load. Dealsite described 128 MW of the 200 MW as going to IT equipment. Two nearly identical rates suggest the buildings are priced off one template, consistent with the prefabricated modular construction LG Uplus says shortens builds by several months. That reading is TechTimes' inference.
Customers' hardware sits outside these ceilings. A single Nvidia Vera Rubin rack can draw up to 200 kW and costs an estimated $7.8 million, per Morgan Stanley figures cited by Edaily. At that density a megawatt holds about five racks, roughly $39 million of hardware, or about 3.6 times the building ceiling per megawatt. Part of campus power goes to cooling and conversion losses, so the true ratio is lower.
On its Nov. 4 earnings call, LG Uplus said customer demand was secured for Buildings 2 through 4. Building 1, a roughly 50 MW building due for completion in June 2027, has contracts with domestic and foreign customers. Samsung Securities analyst Choi Min-ha said it was fully ordered before opening.
The demand confirmation for the later buildings is narrower than it sounds. Sateconomy reported that LG Uplus has not disclosed customer status for Buildings 2 and 3, and that confirmed demand does not mean contracts are complete. Chief Financial Officer Myunghee Yeo described the project's structure as relying on contracts of 10 to 15 years to support capital efficiency, though the report does not confirm every contract has that term. Yuanta Securities analyst Lee Seung-woong sees limited utilization risk because much capacity was leased before completion. Shinhan Investment analyst Kim Ah-ram noted Building 4's opening moved up two years, from 2030 to 2028, and estimated about 2 trillion won ($1.50 billion) of disclosed investment will concentrate in 2027 and 2028.
Conventional data center racks draw 5 to 10 kW per rack, while a Vera Rubin rack can draw up to 200 kW, a density that strains air cooling. Edaily reported that Paju's dual piping supports hybrid cooling, serving both air cooling and direct-to-chip (D2C) liquid cooling when racks sit on both sides of air-conditioning rooms centered on each floor, and that LG Uplus is preparing for 100% liquid cooling. Direct-to-chip systems mount cold plates on processors so flowing liquid carries heat away at the source. LG Electronics supplies free-cooling chillers, LG Energy Solution supplies UPS batteries, and LS Electric is co-developing an 800V DC power distribution system that reduces losses by cutting AC/DC conversions.
The tradeoff is complexity. Liquid removes more heat than air, but leaks can damage electronics and the plumbing needs testing and maintenance. LG Uplus says its liquid cooling is about 24% more energy-efficient than air cooling, a company figure from its own tests.
The economics follow from the engineering. On its Aug. 6 call, LG Uplus said AI data center (AIDC) revenue has a space fee and electricity charge, and that liquid-cooled halls should command higher unit prices. Daishin Securities analyst Kim Hee-jae estimated Buildings 2 and 3 hold about 65 MW of IT capacity and put total LG Uplus data center capacity at 165 MW now, rising to about 400 MW by 2030. Daishin also suggested GPU colocation could more than double revenue per unit of capacity, an analyst projection, but LG Uplus has not disclosed unit rates or its power procurement cost. For tenants, the undisclosed power pass-through will shape total cost as much as the rack-space rate.
AIDC revenue reached 131.7 billion won ($99 million) in Q3, up 27.7% from a year earlier and 6.1% from the prior quarter. The Fact attributed the growth to colocation leasing and DBO revenue, where DBO means design-build-operate. Group revenue fell 0.7% to 3.98 trillion won ($2.99 billion), while operating profit rose 84.1% to 297.6 billion won ($223 million); Money Today Broadcasting credited a base effect from one-time labor costs in the prior year along with efficiency gains. Standalone capital expenditure reached 569.8 billion won ($427 million), up 30.1%.
By TechTimes' arithmetic, the 2.75 trillion won ($2.07 billion) in ceilings equals about 5.2 years of AIDC revenue at Q3's annualized pace of roughly 527 billion won ($395 million). Most of that spending has yet to produce billable capacity: Building 1 targets June 2027 completion, and the four buildings are due online in sequence through 2028. Sateconomy flagged revenue lag and depreciation as margin questions, with power costs undisclosed.
On cash, views split mildly. Daol Investment & Securities analyst Lee Da-yeon rated AIDC cash-flow risk smallest among carriers, while another analyst, identified only as Kim, expects no share buybacks in 2027 or 2028. CFO Yeo said 2027 capital spending will rise from this year's level. On the Aug. 6 call she said this year's spending fits within EBITDA and that the company had no plan to raise outside funds. The phase 3 filing as reported does not name a funding source, so the financing mix for 2027 is still unconfirmed.
LG Uplus is running two to three DBO projects with outside asset managers, letting it add capacity without owning every building. A colocation operator rents space, power and cooling to tenants who own their servers. A DBO contract has the operator design, build and run a facility for an outside owner, earning construction and operating service revenue.
Dealsite reported a 2030 target of 400 MW, split into 270 MW of direct investment including Paju and 130 MW from DBO. Digital Daily's June report cited a 600 MW 2030 target, a gap the sources do not reconcile. The company has also targeted 5 trillion won ($3.75 billion) in cumulative AIDC orders by 2030. With AIDC revenue of 422 billion won last year ($317 million), Edaily calculated that hitting it requires annual growth above 30%.
LG Uplus markets 27 years of 99.999% uptime, a company claim. The same company faces an open referral to investigators: on July 30, South Korea's Personal Information Protection Commission (PIPC) announced a referral to investigators after a July 29 plenary vote, alleging LG Uplus reinstalled operating systems on servers and then disposed of them before the commission's breach investigation began. The PIPC said this made it harder to establish how the leak happened and may amount to obstruction, and it asked police to assess criminal liability. LG Uplus said police are already investigating the matter and that it will cooperate. Seoul police said on April 20 that three suspects had been booked after a March 20 search of the company's Magok office in Seoul. The allegations concern breach evidence, not Paju, but they bear on whether tenants trust the operator with AI workloads.
Phase 3 makes Paju a roughly $2 billion commitment in ceilings, priced at about $10.8 million per megawatt of campus power for the two latest phases, with tenants' hardware costing several times that on top. The first real check arrives when Building 1 opens in June 2027 and shows whether 10-to-15-year contracts turn into occupied, billing racks on schedule. Until then, the figures that decide whether LG Uplus can fund this alone are the 2027 capital spending guidance, the financing mix behind a program of this size and whether the DBO projects convert into signed deals. For a reader sizing AI infrastructure costs, the usable takeaway is the benchmark itself, with its caveats: ceilings rather than spending, one outlet's building split, power rather than IT megawatts, and land excluded.
Currency conversions in this article are approximate and use the xe.com mid-market rate of 1,332.96 won per dollar on Nov. 19, 2026.
Not necessarily. Digital Daily described the figure as an approval limit that may change with business conditions. Sateconomy reported the company set it at about 130% of expected investment to cover price and exchange-rate moves, which would put the base estimate near 607 billion won ($455 million).
In colocation, the operator supplies space, power and cooling while tenants own their servers. In design-build-operate (DBO), the operator designs, builds and runs a data center for an outside owner, earning construction and operating fees. LG Uplus added DBO to its business purpose at its March 24, 2026 shareholder meeting.
A conventional rack draws 5 to 10 kW per rack, while a Vera Rubin rack can draw up to 200 kW, and direct-to-chip liquid cooling offers higher heat removal capacity than air for dense chips.
On its Aug. 6 call, the company said 2026 capital spending fits within EBITDA and that it had no plan to raise outside funds. The Nov. 19 filing as reported names no funding source, and 2027 spending is guided higher.