ChronoScale
ChronoScale (Nasdaq: CHRN) said Wednesday that it signed definitive agreements with STN One Incorporated (STN) for a 50/50 partnership to build an AI data center campus in Odessa, Texas, for an unnamed frontier AI lab. ChronoScale's Form 8-K shows what it gave up to land the order: stock priced at $8 per share, 18% below the previous close, and warrants for up to 8.07 million shares at $0.01 each for the customer. Anyone weighing the headline figure of up to $7.5 billion in contract value needs those terms, because that number covers only a 65 megawatt (MW) first phase and arrives with dilution, bridge debt and cancellation rights attached.
ChronoScale released its announcement at 8:15 a.m. ET, and STN issued its release at 3:18 p.m. ET. The first 65 MW phase is ordered for the first half of 2027 and is expected to produce up to $7.5 billion in contract value over six years. Phases two and three, another 285 MW, have not been ordered, and ChronoScale holds only a right of first offer on that remaining capacity. An amended 8-K says the contribution closing occurred on Nov. 18, the same day.
ChronoScale shares traded down 4.31% to $9.32 at 12:57 p.m. ET Wednesday, while parent Applied Digital rose 2.32% to $14.55 at 1:04 p.m. ET, according to Mugglehead's reported trading figures. Those are midday figures and do not show how the shares closed. CEO Cenly Chen said frontier AI is moving toward commitments "measured in hundreds of megawatts."
The 8-K says the customer, described only as a leading frontier AI lab, holds warrants for up to 8,072,152 shares at an exercise price of $0.01. Half vest in four equal sub-tranches as each GPU tranche is delivered and accepted. The other half vest only if the customer signs a take-or-pay expansion agreement for at least 40 MW at a second ChronoScale site and takes delivery of that capacity.
At the $8 placement price those shares are worth about $65 million, and at Wednesday's midday quote of $9.32 about $75 million, by TechTimes' arithmetic. The customer's exercise cost for all of them would be roughly $81,000. That can be read as a price concession paid in equity rather than in the contract rate, and the shares vest only as ChronoScale delivers or the customer expands.
A separate warrant issued to STN covers up to 850,000 common shares at $0.001 each. It cannot be exercised before May 18, 2027, and shares that have not vested by Nov. 18, 2029 are forfeited. The vesting milestones sit in an exhibit schedule that the filing text does not reproduce.
Structures like this have a precedent. In October 2025, AMD issued OpenAI a warrant for 160 million AMD shares at $0.01 that vests as GPU purchase milestones and share-price targets are met. The industry term for the broader pattern, in which a supplier takes an equity stake in or extends credit to a lab or GPU cloud that then buys from the supplier, is circular financing. A Capacity Global analysis concludes it is not inherently unsound but concentrates risk in ways that are harder to see on a balance sheet.
ChronoScale's release adds a wrinkle. It lists a frontier AI lab among four strategic investors, alongside Nutanix, Empery Digital Inc. and an unnamed storage infrastructure company, but it does not say whether that lab is the customer. The 8-K does not state that the customer bought shares in the placement.
The 8-K puts the $153.0 million common stock placement at about 19.1 million shares at $8.00. Mugglehead calculates that price at about 17.9% below the $9.74 previous close, and the placement shares equal roughly 13.1% of the 145.64 million shares outstanding before it. That share count is a displayed estimate from a third-party data source and may not reflect other recent issuances.
The rest of the $250 million equity component is an unsecured, non-interest-bearing note held by Applied Digital with a $97.0 million principal amount that converts at $8.00 per share, subject to stockholder approval. ChronoScale's release says the note is due to convert in the fourth quarter. By TechTimes' arithmetic, $97.0 million at $8.00 is about 12.1 million shares. Applied Digital kept roughly 97% of ChronoScale after the May spinoff.
Adding the placement shares to the customer warrants gives about 27.2 million shares, or roughly 18.7% of the pre-placement count, by TechTimes' arithmetic. Adding the roughly 12.1 million shares from the Applied Digital note brings the total to about 39.3 million, or roughly 27%, before the STN warrant, any preferred conversions or other issuances. The placement is a private investment in public equity (PIPE), and PIPEs can dilute existing shareholders because new shares enlarge the share count.
No. The release describes a convertible preferred facility of up to $500 million, drawable over four years subject to customary conditions, with an initial minimum conversion price of $12 and about $10 million expected at closing.
The 8-K's Series C conversion terms set the conversion price at the greater of 95% of the lowest five-day volume-weighted average price and the floor price, capped at a $25 ceiling, and the board can adjust the floor but not below $3.60. A draw also requires the lowest five-day price to be at least 110% of the floor in effect. At the $12 floor that threshold is $13.20, about 42% above Wednesday's midday $9.32, by TechTimes' arithmetic.
The amended 8-K lists an initial $10.0 million put notice among the Nov. 18 closing steps. The filings reviewed do not say how that draw meets the 110% condition when the previous close was $9.74.
Unless the stock climbs or the board lowers the floor, most of the $500 million sits behind a price condition. Preferred stock ranks ahead of common stock for dividends and liquidation, and conversion turns that senior claim into common ownership.
Each side contributes $390 million in value for 50% of the partnership, but the 8-K shows the contributions are not $390 million of cash each. STN's side is $251.9 million of agreed asset value for the GPU services agreement, a ground lease and related project assets. The implied balance of about $138 million is payable in cash within 90 days after a qualified project financing covering at least 75% of the project budget. If no such financing happens, STN has no obligation to fund it.
ChronoScale's side is a $220 million partnership convertible note carrying 8% interest paid in kind. It converts automatically into partnership units on the date the antitrust waiting period under the Hart-Scott-Rodino (HSR) Act expires or terminates. Of the note proceeds, $200 million goes to Super Micro Computer "solely to fund the Partnership's purchase of GPUs," and the remaining $20 million goes to the partnership for general corporate purposes. The filing discloses no GPU quantities, models or pricing. Chen's previous role was chief growth officer at Super Micro before ChronoScale named her CEO in May.
A $74.7 million Macquarie term loan at 10% interest paid in kind sits on the partnership and matures 90 days after closing. It is non-recourse to ChronoScale outside the partnership. With the contribution closing on Nov. 18, that maturity falls on Feb. 16, 2027, by TechTimes' count, so refinancing with project financing has to land within about three months.
Neither the release, the 8-K nor the amended filing says whether HSR filings were made or cleared. The 8-K's forward-looking statements flag that the waiting period may not expire before the note matures. Under the HSR Act, the waiting period is usually 30 days once both parties file.
STN builds the campus from factory-built Elemental Data Centers with operating systems installed before delivery. Construction Review Online reports that STN's first unit is designed for 2 MW and 1,024 NVIDIA B300 GPUs, or 1,008 GB300 GPUs after a change to the same footprint, which works out to 512 GPUs per megawatt for that design by TechTimes' arithmetic. The first unit arrived June 11 and was commissioned July 31. ChronoScale's release says GPU configurations vary by phase and names no model, so the B300 figure describes STN's first unit, not a confirmed phase one bill of materials.
STN says the campus combines on-site power generation and battery storage and uses sealed, closed-loop cooling with no process water discharge. Generation technology, capacity, battery size and utility provider are not disclosed, and neither is the water source or annual consumption. Ector County Judge Dustin Fawcett said the project will rely on its own water supply, Construction Review Online reported.
The money math differs sharply from a landlord's. ChronoScale says the contract blends to about $20.8 million of annual revenue per MW across all three phases. By TechTimes' arithmetic, $7.5 billion over six years across 65 MW is about $19.2 million per MW per year. Applied Digital's 15-year lease of 210 MW at Delta Forge 2, valued at about $5.2 billion, works out to about $1.65 million per MW per year, roughly one-twelfth as much. ChronoScale sells GPU cloud compute while Applied Digital leases and hosts data center space, a split The Energy Mag describes, so ChronoScale's revenue per megawatt presumably includes the GPUs and the cost of financing them.
That places GPU replacement risk inside the contract term. Wikipedia's AI data center entry puts GPU lifespans at one to eight years, while each tranche carries a service term of about six years. The timing constraint is tighter: the 8-K schedules the first of four tranches for Q4 2026 and the rest for the first half of 2027, subject to extension, about six weeks before year-end for the first one. The release describes the ordered 65 MW phase as due in the first half of 2027.
The 8-K says the customer may terminate affected tranches for delayed delivery and sustained service-level failures, though cure rights may be available. It also says neither party may terminate for convenience. A substantial portion of phase one is backstopped by credit support from an unnamed investment-grade technology company, and the filings do not say how much.
The release's forward-looking statements warn that the customer has no commitment to order phases two or three, which would leave total contract value substantially lower. If all 350 MW were ordered at the blended rate, annual revenue would reach about $7.3 billion, by TechTimes' arithmetic, which no filing claims.
The order is large against ChronoScale's history. A CMC Markets analysis dated Aug. 28 said the cloud business made up about 99.5% of revenue, nearly all from Together AI, and reported fiscal 2026 revenue of $71.6 million. STN CEO Sabur Mian said the company is built around "controlling the land, power and data centers." STN describes itself as vertically integrated and is based in Pleasanton, California.
Gov. Greg Abbott directed regulators in August to audit data centers seeking grid connection and said no more could be approved to move forward until that process ends. On Sept. 21 he told the Texas Commission on Environmental Quality (TCEQ) to issue no data center permits until the Electric Reliability Council of Texas (ERCOT) and the Texas Water Development Board complete audits. TechTimes reported Nov. 6 that grid officials hope to file audit reports by Dec. 10 and that Governor-elect Gina Hinojosa, who takes office Jan. 19, has called for a moratorium until lawmakers pass protections.
Neither release says whether the campus's grid connection and permits were secured before those pauses. Construction Review Online reports that construction began in May and that an Ector County commissioners' court agenda item on Nov. 12 listed a presentation and possible authorization to sign documents, though the agenda does not show approval. The same report says STN's Odessa plan is 400 MW initially, with a path to 1.6 GW, under the name Project Landman. ChronoScale's release describes 350 MW of campus capacity, so tying it to the 400 MW plan is an inference.
Water is a local worry. Reporting in October 2025 said water supply near Odessa has been a consistent problem for both quantity and quality.
Readers can check the deal against filings as they arrive: whether HSR clearance is announced, whether the first tranche is delivered in Q4 2026, whether the lowest five-day price clears $13.20 for the preferred facility, and whether project financing replaces the Macquarie loan before its maturity. The firm parts are a 65 MW order, a six-year term and an unnamed credit backstop. The conditional parts are most of the preferred money, STN's deferred $138 million, ChronoScale's HSR-dependent 50% stake and every megawatt beyond phase one, and the customer holds warrants and cancellation rights that tie the $7.5 billion to delivery.
Applied Digital retained roughly 97% of ChronoScale after completing the spinoff of its cloud business in May, and Dallas Innovates reported that Applied Digital CEO Wes Cummins is ChronoScale's board chairman.
No. A right of first offer is generally an agreement to negotiate with its holder first, not a right to a sale, and the customer has made no commitment to order phases two or three.
The $220 million partnership note converts into units only on HSR clearance. It matures at the earliest of 91 days after the term loan matures, termination of the contribution agreement before clearance, or acceleration.
They are warrants with a nominal exercise price, here $0.01, that effectively hand the holder shares once vesting conditions are met. In this deal the conditions are tranche delivery and acceptance and, for half, a second-site take-or-pay expansion, so the customer earns the discount as capacity arrives and, for half, only by committing to more.