On November 23, Fengzhushou announced that it has entered into an Equipment Procurement Contract for computing power servers with Company E, valued at RMB 1.664 billion. The company will deliver all equipment in batches, with the delivery period commencing the day after Company E's cumulative advance payment reaches 50% of the total contract amount. Delivery is expected to take 14 to 20 weeks, with an additional grace period of up to 2 weeks. Within three working days after the contract takes effect, Company E is required to pay a 50% advance payment, amounting to RMB 832 million. This contract constitutes a major contract in the company's daily operations and does not require approval by the board of directors or the shareholders' meeting. It does not constitute a related-party transaction or a major asset restructuring.