PJM, the largest U.S. grid operator, submits plan to regulators aimed at shortening wait times for data center power
2 day ago / Read about 0 minute
Author:小编   

PJM Interconnection, the largest U.S. grid operator, announced on Monday that it has submitted a plan to federal energy regulators to accelerate the interconnection process for power plants and high-energy-consuming data centers, though it may require data center companies to bear a larger share of grid costs. PJM covers 13 states in the Mid-Atlantic and Midwest and has struggled over the past three years to keep pace with the growth in electricity demand driven by the rapid expansion of tech giants' data centers. The proposal would merge the feasibility study processes for interconnecting generation, transmission, and large-load facilities such as data centers, shortening the pre-interconnection assessment process from two years to 12 months.