(Left to right) SKT CEO Jung Jae-heon and Hyosung Heavy Industries CEO Woo Tae-hee.(Source: SK Telecom)
SK Telecom (SKT) has formed a strategic partnership with Hyosung Heavy Industries to provide the core equipment for 345kV substations that will power the South Korean telecoms operator's AI data centers (AIDCs).
According to SKT, the 345kV substation is core infrastructure that receives the large amount of power needed by large-scale AIDCs from the grid and converts it into a usable voltage.
The two companies agreed to proactively discuss production and supply plans for core loading equipment to reduce uncertainties that may arise during the procurement process.
"This collaboration will stably secure the core power infrastructure, which is the starting point for AI data centers," SKT CEO Jung Jae-heon said in a statement on Monday. "Through this strategic partnership with Hyosung Heavy Industries, we will strengthen our competitiveness in building GW-class AI data centers and lead the global AI infrastructure market."
SKT, through its new subsidiary SK Hyper, has committed to building AIDCs with a total IT capacity of 15GW by 2035 as part of South Korea's "triple axis" national strategy, which the government announced four months ago. The AIDCs are being positioned as "token factories" that will produce raw AI intelligence rather than being passive storage units.
SKT expects to make its first 5GW of AIDC capacity available in phases, starting from 2029.
Testing advanced power systems
This partnership goes beyond timely power facility deployment – it also aims to jointly build a next-generation technology foundation to boost AIDC power efficiency in the future.
Specifically, the agreement between SKT and Hyosung Heavy Industries also covers testing advanced power solutions such as 800VDC systems. The 800-volt direct current (VDC) is an emerging high-voltage power distribution architecture that is championed by companies like Nvidia, Google, Microsoft and the Open Compute Project, and is designed for next-generation AIDCs and high-density computing racks.
By operating at a higher voltage, the technology reduces the current needed to deliver the same power. For instance, transmitting 1 megawatt at 800 VDC requires only about 1,250 amps, compared to roughly 18,500 amps for a traditional 54 VDC system. Furthermore, traditional data centers repeatedly convert AC power from the grid down through multiple transformers and inverters, eventually delivering 48V or 54V inside the rack. An 800 VDC setup eliminates or simplifies many of these intermediate conversion stages, boosting overall energy efficiency
The partnership between the two companies essentially pairs SKT's data center know-how with Hyosung's heavy power infrastructure capabilities, addressing one of the biggest bottlenecks in scaling AI infrastructure: reliable, high-capacity power supply. It is part of a broader trend among telecom and industrial companies in South Korea and beyond to secure power infrastructure capacity to support the AI boom, as data center operators increasingly face power grid constraints as a limiting factor for growth.